Improve · Section 5: Ground Up Development · Lesson 5.4
The Development Budget
Full lesson transcript
Earlier, you learned to budget a renovation with a real contingency, and here is where that budget stops being enough. A building from the ground carries costs no renovation ever sees. A renovation budget is mostly construction. The building already stands, and it may already be earning rent while the work goes on. A new building has none of that.
There is no income until it is finished and leased. There is land to pay for before the first shovel. There are engineers, fees, and a loan charging interest for two or three years while nothing is earning. The physical construction contract is the number most people think of as the cost, but it is often only a little more than half of the real total. To survive a ground-up project, you have to abandon the idea that the construction estimate is the project budget.
That real total lives in one document, the development budget. which is the complete list of every cost from the purchase of the land to the day the building is stabilized and paying for itself. Every lender will ask for it, every partner should read it, and it is built from six categories. Category one is land, the purchase price plus closing costs plus anything needed to make the land usable. That means demolition of an old structure, environmental cleanup, or a road improvement.
Category two is hard costs, the physical construction, the building itself, plus site work. Site work means grading, paving, utilities, and landscaping. Hard costs are what the general contractor covers. Category three is soft costs, everything that is not physical construction but that the project cannot happen without. Architects and engineers, legal fees, permit fees, and local impact fees.
Soft costs are easy to underestimate because each one looks small on its own. Category four is lease-up costs, the money needed to fill the building. This includes tenant improvement allowances. That is the money you contribute toward building out each tenant space. You also pay leasing commissions to brokers.
Finally, there is the operating deficit. This is the gap between what the building costs to run and what it earns while it is only partly occupied. Category five is financing costs, loan fees at closing and the interest on the construction loan for the whole time it is outstanding. Category six is contingency. A standard contingency on hard costs is often around five percent on new construction.
You also need a separate, smaller contingency on soft costs because fees and approvals surprise people too. Categorizing the budget this way tells lenders and partners that the developer has planned for everything that happens outside the physical construction fence. Here is an illustrative ten-million-dollar budget. Land is one and a half million dollars. Hard costs add five point six million dollars.
Soft costs add one point two million. Lease-up costs add six hundred thousand. Financing costs add six hundred thousand. Contingency adds half a million. Notice that the physical construction contract is just over half of the ten-million-dollar total.
Now a benchmark to test any budget. Soft costs often run roughly a fifth to a third of hard costs. In the example, one point two million against five point six million is twenty-one percent. If a budget shows soft costs at ten percent of hard costs, it is usually because something is missing. The order of those lines matters too.
Land is paid first, almost always with equity. Soft costs come next, before any lender funds. Hard costs are spread over the construction months. Lease-up and much of the interest land at the very end. A budget is a rigid sequence of cash demands, not a static spreadsheet total.
The developer has to be able to meet each one exactly when it comes due. There is one question that exposes a short development budget faster than any other. Ask it of your own team. Show me every dollar between buying the land and the day the last tenant pays rent. That question sets the endpoint.
Many early budgets stop at the certificate of occupancy. which is the local government's approval that the building is safe to use. Stopping there is a mistake. The building still has to be leased, and the loan is still charging interest while it is. The carry.
The carry is every cost of simply holding the project while it is not yet earning. That means interest, taxes, insurance, and the operating deficit. It happens because the building and becomes the carry is dangerous. An illustrative example. A developer budgets eight point eight million dollars and leaves out lease-up costs and most of the interest.
The loan was sized on the smaller budget. The real number is ten million. The one point two million dollar gap becomes an out-of-pocket cash call, often halfway through construction. Watch for this. Check how the interest reserve is sized.
The reserve is a portion of the loan set aside to pay the loan's own interest. If construction or leasing runs past, the reserve dries up. The interest then becomes a personal cash call to the developer. The building is only part of what you are paying for. The budget has to run all the way to the day the rent arrives.