The Feasibility Study

Improve · Lesson 5.3 · 6 minutes · Captions on by default, press CC to turn them off

Full lesson transcript

A feasibility study exists to find the reason not to build while finding it is still cheap. That sentence is the whole philosophy. Everything else is method. Before you own the land, the money you spend is small compared to what comes later. A few hundred thousand dollars on studies, perhaps, against a project of ten million.

Illustrative. Once the land is bought and construction starts, every problem costs ten times more to solve. Some cannot be solved at all. The money spent on them has a name, pursuit costs. What a developer spends chasing a project before deciding to build it, including early design and legal reveal.

Most of it is lost if the project dies. That is expected. A feasibility study answers one question. Can this building be built here for this cost and rented at these rents? It asks if there is enough margin left over to justify the developer's risk.

So the feasibility study is not paperwork. It is the last cheap exit before the spending becomes permanent. Now the rule. It has to happen before any of the studies begin. Set your kill criteria first.

Kill criteria. The specific results written into your own plan beforehand that trigger walking away from the land. An illustrative set. If the yield on cost falls below seven and a half percent, walk. If the early cost estimate comes in more than ten percent over your budget, walk.

If the path to approval takes longer than a year, walk. Why before? Because by the time the studies come back, you will want the project. You will have spent money, walked the site a dozen times, and pictured the finished building. A number that should have ended the project will look like a problem to solve.

Deciding the numerical threshold in advance is how you protect the decision from your own enthusiasm. The study is actually five questions. They run concurrently, answered by different professionals inside a tight due diligence window of two to six months. Illustrative. Question one is the market.

Determining who will rent this building, at what price, and how quickly. It looks at new supply. The buildings already under construction or approved nearby that will compete with yours on opening day. A market study that ignores the two buildings going up down the road is describing a fictional market. Question two is the site.

The survey, the soils report, and the environmental work. Plus one hidden vulnerability, the utility extensions. Bringing water, sewer, and enough electrical capacity from half a mile away can cost as much as a small building. Question three is the approvals. Verifying what the zoning allows and how long public hearings might take.

The core objective is determining if there is a realistic path to approval and what that costs in time. Question four is the cost. An early contractor estimate usually based on rough drawings. It will not be exact. An honest estimate must explicitly list what it leaves out.

Question five is the money. The pro forma. The mechanism that pulls every other answer into one set of numbers. This chart maps the pro forma, projecting the costs, income, and value over time. From it comes yield on cost.

Net operating income divided by total development cost. This yield is compared against the market cap rate to decide if the project makes mathematical sense. These five concurrent investigations all feed a single decision of risk versus reward. There is one specific instruction worth giving every consultant you hire for the study. Here are the words, word for word.

Tell me what would make this fail. Consultants often subconsciously sense what the client hopes to hear. A report confirming those hopes is simply easier to deliver. That single sentence changes their job. It shifts their objective from delivering a pleasing report to look for the project's breaking point.

Demanding the negative gives them explicit permission to find the fatal flaw, protecting the integrity of your data. Now, the mistake. The feasibility study written quietly to say yes. It happens quietly. The rent assumption is nudged up a little because one new building got a high rent.

The construction estimate is simultaneously trimmed a little because the contractor wants the job. The lease-up period is shortened a little because the broker is confident. No single assumption is unreasonable on its own. Together, they are mathematically fatal. This chart shows what compounding optimism costs on a ten million dollar project.

Rents come in ten percent below the study. Costs come in eight percent above it. Leasing takes a year longer than planned. That combination can erase the entire profit, leaving a building worth less than its loan. Compare that to the price of walking away during the study.

Perhaps two hundred and fifty thousand dollars in consulting fees and a lost deposit? Painful, but recoverable. The other outcome often is not. Not every study ends in a clean yes or no. Sometimes it ends in a maybe.

The yield is a little short or the cost is a little high. A maybe is not a failure. It is a negotiation. You can go back to the seller with the soils report and ask for a lower price. You can redesign a smaller building.

You can ask to extend the due diligence window. What you should not do is quietly move the kill criteria until the project passes. At a smaller scale, the same thinking and discipline applies to building one house on one lot. Ask a neutral lender or an experienced developer to read your pro forma cold and listen to which number they question first. A good feasibility study is not the one that says yes.

It is the one you would have believed if it said no.