Improve · Section 5: Ground Up Development · Lesson 5.5
The Development Timeline
Full lesson transcript
How long does it actually take to build a building from the day you find the land to the day a tenant pays rent? Most people guess the construction time, a year, maybe a year and a half. That guess is usually right about construction and badly wrong about the project. The mistake with a development timeline is starting the clock at groundbreaking. That happens when the schedule is built around construction time alone.
For a small commercial building, an honest answer is often three to four years. Illustrative. From the first look at the land to a building that is full and paying, expect forty-four months. Construction is frequently less than half of that total. The rest is time most budgets forget to count.
The developer tells partners the building will be done in fourteen months. Everyone hears fourteen months from today. Building a pro forma and a loan around that construction schedule guarantees a financially vulnerable project. This chart shows how a development timeline runs in five phases. Pursuit and due diligence.
Finding the site, negotiating the contract, and running feasibility studies takes three to six months. Then comes entitlement and design. Getting public approvals and full drawings often takes six months to a year and a half. Permitting comes next. The building department reviews the drawings, and that often takes two to six months, depending on the city.
Then comes construction itself, the visible part. Construction often runs twelve to eighteen months for a small commercial building, from site work to occupancy. Finally, lease-up, from a finished building to a full one. A few months if pre-leased. A year or two if not.
Construction is only about a third of it. Notice where the uncertainty sits. Construction is the most predictable phase because a contractor can schedule it. The phases before it depend on other people, the planning staff, the public boards, and utility companies. The phase after it depends on tenants.
Here is the term that organizes all of it, the critical path. The chain of tasks where any delay pushes back the finish date of the whole project. Pouring the foundation is on the critical path. On a development, some of the most important items on the critical path happen long before construction starts. Successful development requires managing the people and agencies you do not control.
A general contractor follows your schedule, but a public board and a utility company operate entirely on their own. Time on a development is not free because the carry never stops. Land is taxed. Borrowed money charges interest. This breakdown shows an illustrative ten million dollar project.
The combined cost of interest, taxes, insurance, and the partner's waiting capital can run fifty thousand dollars a month or more. A six-month delay in approvals is three hundred thousand dollars. A year of delay in lease-up is more than half a million. Delay also collides with deadlines written into other documents. Land contracts have end dates.
A construction loan has a maturity date. An extension comes with fees and strict conditions. There is a second cost that is harder to see. The market moves while you wait. Rents, construction prices, and interest rates all shift over three or four years.
The project you studied is not quite the project you deliver. Because time translates directly to capital, an invisible delay in a planning office can break a structurally sound investment. Plan the phases before construction at about one and a half times the estimate you are given. If the permit office says three months, plan for four or five. That is not pessimism about any one person.
It is a recognition that. Pre-construction estimates are usually the typical case and a development almost never gets all typical cases in a row. There is a question worth asking every consultant and utility representative who gives you a date. Here are the exact words. What is the longest this has taken here?
Not the typical. Some delays can be managed. The most common way is to overlap phases. Design can continue while approvals are pending. Each overlap carries some risk.
You are spending money before the success of the previous phase is legally certain. But each cannot passively accept timelines. You have to actively stress test and hedge against them through targeted questions and calculated risk. Watch for long lead items. These are pieces of equipment that must be ordered months before they are needed because they are built to order.
The transformer the utility company often supplies, switchgear, rooftop heating and cooling units, and elevators all take many months to arrive. If those items arrive late, the schedule stops. A finished building cannot receive its certificate of occupancy without power or climate control. Ask your general contractor early in design which items have the longest lead times right now. You need to know when they must be ordered for the schedule to hold.
The building takes a year to build. The project takes as long as every approval, every delivery, and every tenant decides it takes.