Improve · Section 4: Running the Job · Lesson 4.4

Inspections and Sign Offs Along the Way

Improve · Lesson 4.4 · 5 minutes · Captions on by default, press CC to turn them off

Full lesson transcript

The permit card taped inside the storefront glass has room for about a dozen signatures, and every blank one is a door that will not open. That card is the local building department's view of your job. Not the contractor's schedule, not the owner's budget. It is just a sequence of moments when someone from outside the job looks at the work while it can still be seen. This chart shows how that sequence runs.

First, the rough inspections. Rough-in, the stage where pipes, wires, and ducts are installed inside open walls and ceilings before anything covers them. There is usually a separate rough inspection for each trade. The sequence then often, an inspection above the ceiling. This inspection sees everything hanging up there before the tiles go in.

Then the finals. A final inspection for each trade, a final for the fire systems, and a final building inspection that looks at the whole. At the end of that sequence comes a different kind of document, the certificate of occupancy. Official permission from the local government for people to use the space. The certificate typically is not issued until the lines on the card are signed.

Without it, a tenant cannot legally open. That physical piece of paper must be verified and signed off before business can begin. The whole subject of inspections comes down to one rule. Nothing gets covered until its inspection is signed off. Not the wall, not the ceiling.

Once drywall goes over a wall, the inspector can no longer see the wiring inside it. Most inspectors will not simply take someone's word for it. They will ask to see it. The only way to see it is to open the wall. The contractor usually schedules the inspections The contractor usually meets the inspector.

That follows from who runs the site. But the owner has a window to ask one question at the right moment. Before the drywall crew arrives, ask the superintendent this. Has everything behind this passed, and can I see the card? It is not an accusation.

A good superintendent will be glad you asked. They are watching the same thing, and they know what an opened wall costs. On the rare job where the answer is, "Not yet, but it will," you have caught the problem while it is still cheap. Now, the named mistake with inspections. Closing it up before it is signed.

It usually happens under schedule pressure. The drywall crew is on site. The electrical inspector is booked out a few days. Someone decides the inspection is a formality, and the walls go up. The inspector arrives, finds the rough electrical line on the card blank, and asks to see the wiring.

The contractor opens a long stretch of finished drywall. They must cut, inspect, patch, tape, sand, prime, and paint. This breakdown chart shows the illustrative cost. Fifteen thousand dollars in labour and two weeks lost as crews are brought back. The contractor may pay for physical repairs, but the owner pays for the schedule.

A waiting tenant pays nothing while walls come back down. There is a second, quieter version. The failed inspection. Inspections fail all the time for small reasons, like a missing cover plate. The trouble is when a failed inspection is reported to the owner as a scheduling detail rather than as a failure, and the reinspection sits unbooked for days.

Here is the decision rule for a re-inspection. Ask exactly what failed and ask for the exact date the re-inspection is booked. A re-inspection with no date is a blank line that is not moving. Unchecked schedule pressure backfires. It always transfers the ultimate cost of the delay directly onto the owner's timeline.

One distinction about inspections is worth holding on to. A passed inspection means the work met the code, a minimum standard for safety. It does not mean the work matches what you paid for. The inspector checks that the outlet is safely wired. The inspector does not check that it is the outlet in your drawings, in the place your tenant asked for it, in the finish you selected.

Passing and correct are two different words. Checking for correctness belongs to the owner's side, usually the architect on a larger job and the owner's own eyes on a smaller one. Other sign-offs sit alongside the building department's. The utility company may not set a permanent meter until the electrical final is signed. A lender funding the work often sends its own inspector before releasing each payment.

A landlord's lease with a tenant may say the space is not delivered until the certificate is in hand. The work is not finished when the crews leave. It is finished when the last line on the card is signed.