Improve · Section 4: Running the Job · Lesson 4.3
Change Orders and How They Multiply
Full lesson transcript
An owner approved one small change on a retail build-out, and by the end of the job, it had turned into eleven. This is a composite. The details are drawn from many jobs, and the shape will be familiar to anyone who has run one. The space was a plain rectangle being fitted out for a new tenant. Midway through framing, the tenant asked to widen the doorway to the back office by a couple of feet.
Easy. A little more framing, a wider door. The owner said yes on the spot. Then the rest arrived, all from that one wider doorway. The wider opening moved a light switch, so the electrician had to reroute a circuit.
The new switch location landed where a thermostat was planned. The thermostat moved and its wiring with it. The wider door needed a different header over it, which the framer priced. The door itself was a different size, so the door and its hardware were reordered, and the original order carried a restocking fee. Touch one thing in a building and you touch whatever it is attached to.
Space is zero sum. The ceiling grid near the opening shifted. which moved a sprinkler head, which needed the fire protection contractor back on site. The sprinkler move needed a revised drawing. which the fire marshal's office to review the plans again.
The flooring transition moved, the base trim changed, and the painter came back for one more wall. Eleven change orders, none of them large. Together, a little over twenty-two thousand dollars. Illustrative and nine days for a doorway. That is how change orders multiply.
Not because anyone is dishonest. A building is a connected physical system. Start with the document. A change order is a written amendment to the construction contract that changes the scope, the price, or the time, signed by both sides. Those three words are the whole anatomy of it.
Scope, meaning what work is added or removed. Price, meaning what it costs. Time, meaning how many days it adds to the schedule or takes away. These changes come from three places. First are owner changes.
The owner or the tenant decides they want something different. The doorway, a finish upgrade, an extra outlet. These are choices. Second are unforeseen conditions. The contractor opens a wall and finds something nobody could have known about.
Rotted framing. An old abandoned pipe. Third are design errors and omissions. The drawings missed something, or two drawings disagree. Only the first of those three is truly a choice.
The other two are what the contingency in your budget exists to absorb. The owner changes are the ones that quietly eat the contingency before the surprises arrive. This chart breaks down how a change is priced, because the price is also where things multiply. A change order usually carries the direct cost of the work, labour and material. On top of that sits a markup for overhead and profit, commonly somewhere around ten to twenty percent, illustrative and set by the contract.
Then you see the subcontractor's markup if a sub is doing the work. The general contractor's markup sits right on top of the sub's price. Then, if the change adds days, you pay the general contractor's cost of staying on site longer. A change that costs one thousand dollars in material and labour can arrive as a change order of fifteen hundred or more. That is simply what it costs to reopen finished work, send a crew back, and manage it.
There is one more way the arithmetic works against the owner. Changes that remove work tend to shrink. If you delete something from the job, the contractor gives back a credit. But the material may already be ordered, the crew scheduled, and some of the markup never come back. A change that removes a thousand dollars of work might return six or seven hundred.
A job that swaps one thing for another, back and forth, loses money on each swing, even when the net scope barely moves. Now, the named mistake with change orders, the verbal go-ahead. It happens on site, usually with good intentions. The superintendent explains an issue. The owner says, "Just do it.
We will sort out the paperwork later." An illustrative cost. A verbal go-ahead on rerouting some duct work. The owner imagined perhaps two thousand dollars. Weeks later, the change order arrives at six thousand five hundred. The work is already hanging in the ceiling.
There is nothing to negotiate against. The owner has lost every piece of leverage a change order normally gives. The most useful moment in a change order's life is before it exists. Here is the question to ask, word for word, before you say yes to anything. What else does this touch?
What does it cost with markup? And how many days does it add? Here is the rule for change orders across the whole job. Once approved changes pass roughly five percent of the original contract, stop and re-examine the scope before approving the next one. Past that point, you are no longer adjusting a design.
You are redesigning a job, one piece at a time, at the most expensive moment to do it. Watch for the blank line for time. A change order with a price and no days, or with the words to be determined, is a change order that has not finished being priced. Ask for the days before you sign it. Many contracts actually require changes to be in writing before the work proceeds.
A real estate attorney can explain what yours says and how a verbal approval might be treated where you are. A change order is never one change. It is one decision with a crowd standing behind it.
