We came in thirty thousand under the other two, and honestly, we just want the work. A contractor says something like that on the phone, and it sounds like good news. Take an illustrative job. Three bids to renovate a suite. Two come in around two hundred and fifty thousand dollars.
The third comes in around two twenty. Same scope, form, same site walk. Thirty thousand dollars is real money. When two higher bids are close and the low stands alone, the market has told you what the job costs. The outlier is the one that has to explain itself.
The question is exactly where that thirty thousand went. An unexplained low bid is not a discount. It is a masked financial risk transferred from the contractor to you. There are only a handful of places a low number can come from. The first place is missed scope.
The contractor did not see something or did not price it. Maybe they missed a page of the drawings. Maybe they did not notice the occupied suite next door that forces night work. The contractor who missed it will want to be paid for it once they find it. The second is cheaper inputs.
That means lower cost subcontractors, lesser materials, or a thinner crew. The cheaper electrician is often cheaper because they are slower, less careful, or less licensed. The third is buying the job. That is the trade phrase for bidding at or below cost to win the work, then recovering the margin later through change orders, which are priced changes to the contract after it is signed. A contractor who buys the job is counting on them.
The fourth is cash. A contractor who needs a deposit to cover payroll on another job will price low to get money moving. That contractor is running on thin ice. Your job may be the one that falls through. Watch for the low bidder who asks for a large deposit before any work starts.
A request for half the contract upfront is usually a sign of a cash problem. Ask what the deposit is for. Tie it to specific materials you can see delivered to the site. These four scenarios show the reality of an artificial discount. It does not eliminate your costs.
It simply delays them until you are trapped in a half-finished project. The fifth reason is the good one. Sometimes a contractor really is more efficient. They own the lift instead of renting it. Their electrician is in-house.
Those reasons are real, and they are worth rewarding. You have to find out which one you are looking at. Here is the decision rule for a low bid. If the lowest bid, after leveling, is more than about fifteen percent below the middle bid, treat it as a question. It is not an automatic win.
You ask the question in a meeting with the bid on the table between you. Ask them to walk me through where your number is lower than the others, line by line. Listen to how the answer sounds. A good answer is specific. They tell you they own our lift.
A worrying answer is general. They tell you they just keep overhead low. That might be true. It still does not tell you where the thirty thousand dollars went. Sometimes, while walking you through it, the contractor finds the miss themselves.
“Oh. We did not carry the fire alarm work. That is not a failure of the conversation. That is the conversation working. Finding that missing cost at the table preserves your leverage.
Finding it after the walls are open destroys it. What if a low bidder's answer is weak answer? You have three honest choices. First, you can ask the low bidder to reprice the job with the missing items explicitly carried in writing. The new number is often still competitive.
Second, you can hire the low bidder anyway. knowingly, and, hold a contingency, which is money set aside for the surprises you expect. If you suspect twenty thousand dollars of missed work, set aside twenty thousand dollars. Third, you can award the job to the middle bidder. Tell the low bidder why.
Be plain and respectfully that you would rather pay a known, reliable price. All three choices put cost certainty ahead of an unexplained discount. They protect you from surprises in the middle of the project. Here is the named mistake with a low bid: taking the discount before you understand it. In an illustrative case, the owner takes the two hundred and twenty thousand dollar bid without asking.
Six weeks in, the change orders start. The missed fire alarms. A larger electrical panel. Patching that nobody carried. By the end, change orders total about forty-five thousand dollars.
The job finishes late, The incoming tenant's rent is roughly eight thousand. Every change orders arrived as a negotiation, with the contractor holding the leverage of a half-finished space. The owner saved thirty thousand at signing and spent more than fifty thousand to get there. They arrived at a finished space late and over budget. The lowest bid is sometimes the right bid.
Take it when the scope is identical, the exclusions are priced, and the contractor can explain the difference line by line. Low is not the problem. Unexplained is the problem. The lowest bid is a price. The right bid is a price the contractor can afford to finish.