Improve · Section 3: Contractors and Bids · Lesson 3.3
Reading a Bid for What Is Excluded
Full lesson transcript
What is this contractor not doing for the price at the bottom of the page? That is the question to ask of every bid before you look at the total. Most people read a bid the other way. They find the number, they compare it to the other numbers, and they skim the rest. But a number only means something once you know what it covers.
The part of a bid that tells you what it does not cover is usually on the last page in smaller type. They draw the edges of the price. Exclusions. Specific item the contractor is not including in the price. It is not a trick.
It is how contractors protect themselves from work they cannot see or control. The trouble is that the owner usually still has to pay for most of it. You will end up paying someone. Here is an illustrative case. An owner receives two bids to renovate a vacant suite in an occupied building.
One is one hundred eighty thousand dollars. The other is one hundred ninety-five thousand. The owner picks the lower bid. But they fail to read the exclusions on the final page. The lower bid left out the permit fee.
It excluded dumpsters. It left out patching and painting after the other trades. And it excluded all after-hours work. The building has tenants on both sides. That means the noisy work has to happen at night.
The contractor priced regular hours and excluded the premium. Those exclusions add up to about twenty-five thousand dollars. The cheaper bid was really ten thousand dollars more expensive. Because the owner discovered it one surprise at a time, each item arrived as an argument instead of a line on a bid. Here are the exclusions that show up most often on small and mid-size commercial jobs.
You will see several of them on almost every bid. Permit fees are common. Many contractors will pull the permit but exclude the fee. Dumpsters and haul-off are another. Somebody has to remove the demolished walls.
On a bid that excludes it, that somebody is you. Then there are trade-specific apps. The electrician cuts holes in the drywall to run new wire. If every trade excludes patching and painting, nobody does it. Bids also almost always exclude testing for asbestos or lead paint.
Now consider a second word, allowance, a placeholder amount in the bid for something not yet chosen. An allowance of five thousand dollars for light fixtures means the bid assumes you will choose five thousand dollars of fixtures. Choose nine thousand? You pay the difference. Allowances are useful, but a contractor can make a bid look low by setting allowances unrealistically low.
A contractor who writes a long, clear exclusions list is usually doing you a favor. They are telling you exactly where their price ends. The contractor to worry about is the one with a vague list. Assumptions on a bid deserve a slower read, too. An assumption is a condition the contractor has decided is true.
They price the work as if it were true. This bid assumes the existing electrical service is adequate. If the electrical service turns out to be too small for the new layout, an illustrative upgrade can run fifteen to twenty thousand dollars. The assumption says that cost is yours. Watch for the words by others.
That means someone other than this contractor does it. Very often, the other is you. You will also see the phrase as required. That usually means the contractor will do it, but has not priced how much of it there will be. Existing to remain means the contractor assumes something already in the building works.
If it turns out to be broken, fixing it is extra. Every assumption and vague phrase does the same job. The contractor is shifting the financial risk of the unknown directly onto your balance sheet. So read a bid in a different order than it is printed. First, read the description of the work.
Then the exclusions. Then the assumptions. Then the allowances. Only then look at the price. By the time you reach the number, you will know what it is a number for.
Before you compare totals, level the bids. Leveling. Pricing every exclusion and every thin allowance on each bid. Every total then covers the exact same work. Here is an illustrative threshold.
If the excluded items on a bid add up to more than about five percent of its total price, send it back to the contractor before you go any further. Here are the words to use when you do. Please confirm that everything in the scope is included in your price, and list anything that is not with a price to add it. That sentence does two things. It puts the burden of finding gaps on the person who knows the work best.
And it turns every vague exclusion into a hard number you can compare. The price on a bid tells you what you will pay. The exclusions tell you what else you will pay.