Underwrite · Section 4: The Capital Stack · Lesson 4.8
Building a Stack for a Real Deal
Full lesson transcript
"The bank will lend sixty-five percent of cost, and we still have to find three and a half million dollars." One partner says it to another across a conference table. This is a composite, and the numbers are illustrative, but the conversation is one that happens on nearly every deal of real size. The pieces from the previous seven lessons now have to become one decision. Here is the deal. A well-located suburban office building priced at nine million dollars.
Closing costs, improvements, and reserves of about one million. It takes ten million dollars all in to buy it. Today, the building earns six hundred thousand dollars of net operating income. After the improvements and some leasing, the plan says it will earn seven hundred and fifty thousand. That future number is stabilized income, the income the building earns once the plan is complete and occupancy is normal.
Building a capital stack is simply bridging the gap between that ten million dollar cost and what the stabilized income can safely carry. Step one is always the same. Size the senior loan first because it is the cheapest money and it sets the rules for everything else. The bank offers sixty-five percent of cost, six and a half million dollars at around six and a half percent. Repaid over twenty-five years, the yearly payment is roughly five hundred and twenty-five thousand dollars.
That leaves a gap of three and a half million. The operator has one million. The question is how to fill the other two and a half. There are three realistic versions. Version one All of it all from partners as common equity.
No other lender. Version two uses as much gap money as possible, securing a one and a half million dollar mezzanine loan at twelve percent. Version three Somewhere between them, splitting the difference with a smaller mezzanine loan and three quarter million. Version two looks best on a projection. The operator gives away less ownership and projects a higher return.
We have to test all three versions to see if they can survive reality. One note before the tests. Preferred equity could replace the mezzanine loan in versions two and three, and the arithmetic would be nearly identical. For these tests, treat a preferred return exactly like a loan payment because in practice, the operator must pay it or face the consequences. The first test is coverage.
Take stabilized income and divide it by every payment that comes ahead of common equity. In version one, seven hundred and fifty thousand against the bank's five hundred and twenty-five thousand is about one point four. Comfortable. In version three, the ratio drops to about one point two. Tight.
In version two, against seven hundred and five thousand in combined payments, the ratio is barely above one, and that is after the plan works. On today's income of six hundred thousand, version two does not cover its payments at all. The operator would be feeding the building cash every month until the leasing is done. The second test is the wipeout price. The sale price after costs at which common equity comes back as zero.
In version one, the wipe-out price is six and a half million, meaning the owners survive a thirty-five percent fall from cost. In version two, they are wiped out by a twenty percent fall. Pushing the gap money to its limit directly sacrifices the property's ability to absorb normal market bumps without bankrupting the owners. The third test is refinance. At the end of the loan term with a higher rate, will a new loan repay everything ahead of the owners?
Version two needs the largest refinance from the thinnest cushion. The fourth test is carry. Is the interest reserve and the owner's cash cushion big enough for the plan plus about six months? In version two, the heavy mezzanine interest has to be carried all the way through the lease-up. Now the rule for building a capital stack.
Size senior debt first, then fill the gap in whatever combination keeps two tests passing. Stabilized income covers every payment ahead of common equity at least about one point two five times, and common equity can survive at least about a twenty percent fall in value. Those thresholds are illustrative and markets vary, but a stack that fails both is not a plan. It is a wager. By that rule, version two fails.
Version three sits right at the edge. Version one passes easily. The partners in this composite chose version one and gave up a larger share of the upside to their investors. They accepted a smaller slice of a deal that could survive a bad year over a larger slice of a deal that could not. Here is the request to make of every capital stack, whether you are the operator or an investor being shown one.
Here are the words. Show me this deal if everything is ten percent worse. Ten percent lower income. Ten percent lower value at sale. A slower lease-up.
A good operator can produce that version quickly, and it is usually more informative than the one on the cover. Now the mistake. Call it building the stack backwards. The operator starts from the cash in hand, subtracts it from the price, and fills the gap with whatever money says yes. The cheapest money is taken to its limit.
The most expensive money fills the hole, and nobody tests the combination as a whole. What does it cost? In version two, an illustrative delay of nine months in leasing is enough. Income stays near six hundred thousand, but payments stay above seven hundred thousand. The mezzanine loan defaults, the lender moves on the pledged ownership, and the operator and partners lose their combined two million dollars of equity.
The building itself may be fine. The stack was not. A mortgage broker can help size the senior loan. A real estate attorney should read every document that sets the order, and a CPA can explain how each version affects taxes. When a stack only works because of the last million, look hardest at the terms of that million.
It takes the most risk for the least cushion. A good capital stack is built from what the building can carry, not from what the buyer can find. You can now test a mix of debt and equity against actual property income to ensure a deal survives a bad year. The structure of partner money, how it is divided, and what the law requires is the subject of the next section.