Improve · Section 6: Entitlements and the Public Process · Lesson 6.4

Utilities, Stormwater, and Impact Fees

Improve · Lesson 6.4 · 6 minutes · Captions on by default, press CC to turn them off

Full lesson transcript

The sewer runs right past the lot, so we are fine, the buyer said, and the engineer asked which way it flowed. Sewer lines mostly run on gravity. Waste flows downhill. If the pipe in the street sits higher than your building, waste cannot fall into it. You may need a lift station, a small pumping plant that pushes waste uphill.

On a modest commercial site, that can cost a great deal. An illustrative example. A buyer pays eight hundred thousand dollars for a lot, assuming the connection will be simple. After closing, they learn the main is higher than the site. The utility requires a private lift station and an upgrade to a downstream pipe.

Illustratively, that is two hundred fifty thousand dollars of cost and about six months of design and approval. The pipe was right there. It just was not usable. Three costs sit underneath almost every piece of raw land and every big change of use. Utilities, stormwater, impact fees.

None of them appear on the zoning map. All of them can decide whether a project works. Start with utilities and with one idea, capacity. Whether the system can actually take on your project. Water, sewer, power, and gas have limits.

A water main may not deliver enough pressure for fire protection, which for commercial buildings is often the harder test. Fire flow, the volume of water a hydrant system must deliver to fight a fire in your building. A larger building typically needs more. If capacity is short, someone pays to fix it. Very often that someone is you.

Utilities commonly require the developer to build the extension and turn it over to the system. Here is the exact question to ask each utility. Do you have the capacity to serve this project and will you confirm that in a will serve letter? The will serve letter. A written statement from a utility that it can and will serve a specific project, often with conditions.

Lenders frequently want one. So should you. A verbal yes on the phone is encouraging. A letter is what you can rely on. A utility that hesitates to put it in writing is telling you something.

Second, stormwater. When you cover land with roofs and pavement, rain that used to soak in now runs off, faster and in larger volume. Most places require the new project to manage that water on site. This chart shows the common standard. The rate of water leaving after construction may not exceed the rate before construction.

To meet it, you build detention. Storage that holds runoff on site and releases it slowly. A dry pond or an underground vault. Detention costs money twice. It costs to build and it takes land.

An open pond might consume an illustrative 10 to 15% of a small commercial site. That is land that cannot hold a building or parking. Existing buildings are not exempt. A redevelopment that disturbs more than a certain area of ground can require the whole site to be brought up to current stormwater standards, even where the old building never had a pond at all. Your civil engineer sizes this early.

Because it directly limits your buildable area, it belongs in the price you pay for the land. Third, impact fees. A one-time charge a local government collects from new development to pay for its share of public infrastructure. On top of them sit tap fees. Those pay to physically connect to the water and sewer systems.

Impact and connection fees are set by schedule, and the schedule is usually public. Most charge by size and by use. That second part matters. A restaurant typically pays more than a store of the same size because it uses more water and draws more traffic. Impact fees are usually paid at the building permit, not at closing on the land.

That timing is why they get forgotten. They do not show up in the purchase price. They show up in the construction budget later when there is less room to absorb them. Illustratively, on a 10,000 square foot commercial building, combined fees might range from tens of thousands of dollars in one place to several hundred thousand in another. That range is exactly why you get the local number in writing for your exact use.

Here is the decision rule for utilities, stormwater, and fees. Before your due diligence period ends, have capacity confirmed in writing by every utility you need. A stormwater concept from your civil engineer and a written estimate of every fee for your exact use. Going hard. The point in the contract when your deposit is no longer refundable.

Do not let the contract go hard on a guess. If you cannot get those three pieces of information before the deadline, ask the seller for an extension or walk away. This logic scales down to existing buildings as well. A change of use can trigger new impact and tap fees, even with no new square footage. Turning a small shop into a restaurant can mean a new grease interceptor, a larger water meter, and a fee bill that surprises the tenant and the owner.

Who pays is a lease question worth settling before signing. Everything here varies by place. Fee schedules change, often yearly. Your civil engineer, the utility providers, and local planning staff are the sources of the real numbers. Land is priced by the acre, but it gets built by the pipe.