Improve · Section 2: Scoping the Work · Lesson 2.6
Phasing Work Around Occupied Space
Full lesson transcript
"You can renovate anything you like as long as my customers never know you are there." A tenant said that to an owner who was about to renovate the building around them. It is a fair request. It is also impossible to meet in full. What you can do is divide construction into a sequence of stages. This is called phasing.
Parts of a building stay occupied and working while other parts are under construction. A contractor who has to work at night, move crews between areas, and build temporary walls will charge more than one handed an empty building. Often ten to twenty percent more as an illustrative range. That cost belongs in the scope and the budget from the start, not in a change order later. This chart compares the phasing premium against the rent you keep by staying occupied.
The comparison gives you a simple decision rule. When the rent kept exceeds the extra cost, you phase the work. When it is not, you wait for the space to empty, and you build faster and cheaper. Phasing is never just a default courtesy. It is a calculated financial decision chosen only when the math proves the retained rent outweighs the construction premium.
Once you decide to phase, you ask four questions for every stage of the work. Question one is: Can they get in? Every occupied tenant needs a working entrance, a clear path from parking, and signs if the route has changed. Question two is: Can they still operate? A tenant requires power, water, heating and cooling, data, and a working restroom.
The phasing mistake is the surprise shutdown. This happens when a utility goes down without warning. An illustrative example. A contractor needs to connect a new water line to the building and shuts off the water in the middle of a business day without telling anyone. A salon has clients in the chair.
A restaurant cannot run its kitchen. The connection takes four hours. Call it fifteen thousand dollars in concessions and a relationship that takes a long time to repair. The same connection planned for an evening when both were closed with a week of notice would have cost a few hundred dollars in overtime. If any utility goes down even briefly, it must be an intentional planned shutdown with advance notice.
It is never an accident. Question three is: Can they get out? Every occupied space needs a legal exit path and working fire alarms and sprinklers throughout the work. This is a life safety code requirement, not a courtesy. When a life safety system has to be taken out of service, jurisdictions often require a fire watch, a trained person walking the building continuously while the system is down.
It is inexpensive compared with the alternative, and it is often required. Question four is: Can they tolerate it? Noise, dust, vibration, and smell. This is where most complaints actually come from. You choose physical tools to answer that question.
Temporary walls built from the floor to the structure above seal the work away. Sometimes contractors use negative air, keeping the work area at slightly lower air pressure than the space around it, so dust flows in rather than out. You also use sequencing, doing the loudest work closest to a tenant when that tenant is least busy. A restaurant's slow hours are not a dentist's slow hours. Minimizing a tenant's physical discomfort is not about being polite.
It is about actively engineering construction methods to prevent operational interference. The lease matters here. Most commercial leases give the landlord some right to enter and make improvements, but they also protect the tenant's right to use the space without unreasonable interference. When disruption breaks that right, some leases provide rent abatements, a reduction or pause in rent when the space becomes legally unusable. Before each phase of the work starts, the tenants should hear from you.
Here are the exact words to say. Here is what you will hear, when you will hear it, and who to call if it is worse than that. That sentence gives them three things: what to expect, so nothing surprises them; when, so they can plan around it; and a person, so a complaint has somewhere to go other than a lawyer. Give them. The phasing plan that only exists in the contractor's head, ask to see it on paper before you sign the contract.
For each phase, it should say which areas are closed, how every occupied tenant gets in and operates, and which shutdowns are planned. A written phasing plan is the ultimate operational proof of the lease agreement. Phasing is how the building keeps its promises while you break a few walls.