Improve · Section 3: Contractors and Bids · Lesson 3.8

Negotiating Price Without Losing the Relationship

Improve · Lesson 3.8 · 6 minutes · Captions on by default, press CC to turn them off

Full lesson transcript

Earlier, you learned why the lowest bid is usually not the best one. Here is where that breaks. You still have to bring the right bid down to a price you can afford. You have leveled the bids. You have picked the contractor you trust, and their number is still more than your budget.

Maybe by ten thousand dollars, maybe by forty. Now, you have to negotiate with someone you are about to spend months working beside and whom you would like to call again in year three. Most owners negotiate the wrong thing. They negotiate the contractor's margin. They ask if the other guy was cheaper or if the contractor can knock ten percent off.

Those questions all ask the contractor to earn less for the same work. Sometimes they will agree, but a contractor who agrees to earn less on your job has to recover it somewhere or accept a job they now resent. Neither is good for you. Treating the contractor's margin as an adversary is a zero-sum game, and it ultimately damages your own project. The better approach is to negotiate the job, not the contractor.

There are four places where price can come out of a job without coming out of the contractor's pocket. The first is scope. Is every item in the scope truly needed now? Could the break room cabinets wait until the next tenant? The cheapest work is the work you decide not to do.

The second is specification. Value engineering: finding a less expensive way to get the same result. A lighting fixture that performs the same at half the cost. The contractor usually knows these options better than you do, so ask them. The third is schedule.

Work that can be done during regular hours instead of nights and weekends costs less. A deadline with some slack lets the contractor fit your job around their others instead of pulling crews off paying work. The fourth is terms. Contractors carry the cost of the job until you pay them. An owner who pays on time every time is worth money to a contractor.

So is an owner who makes decisions quickly, provides clear access to the building, and offers the chance of more work. Those are things you can give that cost you little. By adjusting these four levers, you act as a problem solver rather than an adversary. You extract costs from the project without threatening the contractor's livelihood. Here is the question that opens the way to a lower price.

It is the most useful sentence in a construction negotiation. If we needed to bring this down by twenty thousand dollars, where would you look first? This chart shows how asking that question works in an illustrative case. A contractor bids two hundred and forty thousand dollars to renovate a suite. The owner's budget is two-fifteen.

The owner asks the question. The contractor comes back a few days later with a short list. Keep the existing ceiling grid and replace only the tiles, saving about eight thousand. Move most of the demolition to regular hours since the neighbouring tenant agreed to it, saving about six thousand. Swap two custom light fixtures for standard ones that look nearly identical, about seven thousand.

Phase the break room into the next tenant's job, about five thousand. And in return for payment within ten days of each approved application, the contractor trims a further two thousand. That is twenty-eight thousand dollars removed from the bid. The owner picks the items worth taking, lands inside the budget, and the contractor's margin is untouched. Both sides walk out ready to work together.

Here is the decision rule. Never ask for a price cut of more than about five percent without giving something back in scope, specification, schedule, or terms. Here is the negotiating mistake. Call it bid shopping. Bid shopping means taking one contractor's price to another and asking them to beat it, or telling your preferred contractor what the low bidder charged and asking them to match it.

This diagram shows how bid shopping costs you in an illustrative case. An owner receives a two hundred thousand dollar bid from a contractor they want. They tell the contractor a competitor came in at one eighty-five and ask them to match. The contractor, wanting the job, agrees. Now, the contractor needs to find fifteen thousand dollars, so the job gets their second crew instead of their best one.

Every small question in the field becomes a change order because there is no room left to absorb anything. By the end, change orders have returned most of the fifteen thousand. The job ran slower. The owner won the negotiation and lost the contractor. There is also a way to say no to a price without damaging anything.

If the number still does not work after you have explored the four places, say so plainly and say why. Your price is fair for what is in it. It is just more than this building can carry right now. Can we look at a smaller first phase? Watch for this.

A contractor who agrees to a large cut too quickly without asking what changes in the job. After it is different about the work at this new price?" If the answer is nothing, then something will be different later and you will not get to choose what. Take money out of the job, not out of the contractor, and they will still answer the phone next time. You can now level bids and successfully negotiate a fair price that gets the project built. Next, we will cover how to manage work and money once the contract is signed because true leverage exists only before that contract is signed.

This negotiation is the final safeguard of a project's financial health.