Actual Versus Budget, Month by Month

Evaluate · Lesson 1.2 · 6 minutes · Captions on by default, press CC to turn them off

Full lesson transcript

"Repairs ran a little over again, but it should all even out by the end of the year." That is a property manager speaking, and it may be one of the most expensive sentences in the business. Not because it is dishonest. It is usually said in complete good faith. It is expensive because it turns a signal into a shrug. The report behind that sentence is the budget comparison.

Some people call it the variance report. It puts two numbers side by side for every line of the operating statement. What you planned to earn or spend and what actually happened. The difference between them is the variance. The gap between the plan and reality shown in dollars and in percent.

An illustrative example. The budget says repairs will cost about four thousand dollars a month. This month, actual repairs came in at six thousand. The variance is two thousand dollars over or fifty percent. A good comparison shows each line two ways.

The current month and the year to date, meaning all the months so far this year added together. The month tells you what just happened. The year to date tells you whether it is a pattern. One bad month in repairs is a burst pipe. Five months over budget out of six is a building telling you something.

Read correctly, this report diagnoses the physical health of the property in real time. It tells you exactly what is failing before the damage compounds. So how do you read one without drowning in it? A small retail center might have forty lines on its operating statement. Nobody should investigate forty lines.

Most of those lines will sit close to plan most of the time. Taxes are set by the county. Insurance is fixed by a policy. Management fees follow the rent. The lines that move are repairs, utilities, cleaning, and above all, rent itself.

A good reading spends nearly all of its attention on a handful of lines and gives the rest a glance. Here is the rule for reading a budget comparison. Question only the lines that are off by more than ten percent and by more than a set dollar amount, say one thousand dollars in the same month. Both conditions together. The percent alone flags tiny lines.

A landscaping line that doubles from two hundred to four hundred dollars is one hundred percent over, and it does not matter. The dollars alone miss the pattern on the smaller lines. Together, they usually leave three to five lines worth a real question. The thresholds are illustrative and scale with the building. A larger property might use five percent and five thousand dollars.

What matters is choosing them before you look. So the report decides what gets questioned, not your mood that day. This strict filtering mechanism protects an owner's most valuable asset, their attention. It keeps them from drowning in operational noise. Then for each of those surviving lines, ask one thing.

Is this timing or is this real? A timing variance is money that was planned, just not in this month. The budget put the insurance payment in March, and it was paid in February. February looks terrible. March will look wonderful.

By year-end, nothing changed. Timing variances are why the year-to-date column exists. A real variance is money that will not come back. Repairs running over because the heating and cooling units are aging. Utilities up because a tenant now runs longer hours.

Rent under budget because a suite you expected to lease in the spring is still empty. Those do not even out. They compound. The income side deserves the same attention as expenses. Owners tend to study the expense lines and skim the income.

But a rent line under budget month after month is often the first place a leasing problem shows up well before the vacancy feels real. When a line in the budget comparison crosses your threshold, here is the question to ask the manager in these words. Is this timing or is it real? And if it is real, what does the rest of the year look like? That question does two things.

It gives the manager an easy way to say it is timing if it is. And if it is not, it asks for a revised view of the year instead of a hope that things even out. A good manager will welcome it. It is the question they would ask themselves. That specific language forces a clear plan for the remaining months.

It requires the manager to solve the math today rather than hoping it resolves itself by December. Now, the named mistake. Call it averaging away the signal. It is the opening sentence taken at its word. An owner hears that repairs are over but will even out.

They accept it in the second month, again in the fourth, again in the seventh. By year-end, repairs are over budget by about twenty-four thousand dollars illustrative. The cause was two aging rooftop units being patched every few weeks. Replaced in the spring, they would have cost about thirty thousand dollars together and ended the repair calls. Instead, the owner paid twenty-four thousand in patches and still has to replace both units.

The money was not lost in any single month. It was lost in the conversation that kept saying it would even out. There is a quieter version of the same mistake. A budget written carelessly makes every comparison meaningless. If the budget simply copies last year and adds a few percent, the variances will not tell you much because the plan was never really a plan.

This works the same on a single rental house. The budget is simpler, maybe ten lines, but the question is identical. A water bill over budget three months running is a leak somewhere, and it is not going to even out. Watch for this. The same line crossing your threshold two months in a quiet year.

They can be timing. Twice on the roof and the same direction is almost never timing. That is the moment to ask for the revised view of the year before a third month arrives. Applied with strict discipline, the budget comparison isolates the physical failures of a building early. The paperwork points directly to the actual problem on the ground.

Nothing evens out on its own. A variance is the building asking a question, and it keeps asking until someone answers.