Getting Real Bids on Recurring Services

Direct · Lesson 4.5 · 5 minutes · Captions on by default, press CC to turn them off

Full lesson transcript

Three bids for the same service are only worth comparing if all three bidders were pricing the exact same job. That sounds obvious. It is almost never what happens. An owner calls three landscaping companies and asks for a price to take care of the grounds. Each company walks the property and imagines a different job.

One pictures mowing and edging. Another adds pruning and leaf removal. The third adds the irrigation system. Three prices come back, and the owner picks the lowest. And the lowest was not cheaper.

It was simply smaller. Without defining the work upfront, an owner is simply buying a vendor's assumptions. They are not comparing actual market costs. Recurring services are the work a property pays for over and over on a cycle: landscaping, parking lot sweeping, pest control, janitorial cleaning. Each one is a modest monthly bill.

Together, they are often one of the largest lines in an operating budget, and they renew quietly year after year. A one-time project, like a new roof, is bid completely differently. Here, the subject is the steady repeating work. Allowing these recurring contracts to roll over without asking if the price still makes sense is an easy way to bleed a property's cash flow. The fix is a single document prepared before anyone is called.

A scope of work, a plain written description of exactly what the service includes. A useful scope answers five questions. First is what exactly? This is a plain list itemizing every specific task the crew will perform. Second is how often?

The required frequency for each task. The frequency drives most of the price, so it must be identical for every bidder. Third is to what standard? What done looks like. A clear standard gives you something to point to when the work slips.

Fourth is what is excluded? Things the vendor will not do or will charge extra for. The exclusions are where cheap bids hide their savings, so name them yourself. Fifth is the terms, the logistical rules of the property, including where the crew parks, who they check in with, and the insurance you require. A properly built scope removes imagination from the equation entirely.

Any two companies reading it would picture the exact same physical job. Once a written scope of work exists, the bid process is simple. Get three competitive bids based strictly on that same written document. Send every bidder the scope and one sentence with it, word for word. "Please price exactly this scope and list separately anything you would add or remove." Walk the property with each bidder.

Show them the problem areas. A bidder who will not walk the site before pricing is guessing. When the written scope with a physical site walk guarantees every vendor is pricing the exact same physical reality. The numbers finally compare. If one bid comes in well below the other two, treat it as a question, not a win.

An illustrative threshold is twenty percent. If one bid is more than twenty percent under the average of the others, something is different. This leads to a named mistake: taking the cheapest bid on a vague request. An owner asks for a landscaping price with no scope. The low bid is eight hundred dollars a month.

The next two are around a thousand. The owner signs the cheap one. Then the invoices start arriving. The cheap bid achieves its low monthly rate by stripping out standard tasks. Leaf removal and shrub pruning get billed later as separate extras.

By the end of the year, the extras total an illustrative four thousand dollars. The cheap bid cost more than the expensive one. Cheap bids operating without a scope are expensive traps. They hide behind vague terms and are guaranteed to cost more in time and approved. There is a quieter way to overpay on a recurring service: the incumbent vendor.

A company that has held a contract for years without being asked to compete often drifts upward in price and downward in attention. When you do rebid the work, watch for bids that come back in different shapes. One quotes a monthly flat fee while another prices per visit. Before you compare them, mathematically convert every bid to the same shape. If a bid refuses to fit that shape, you have a clear warning that the vendor is attempting to sell you a completely different job.

The point of a disciplined bidding process is not necessarily to change vendors. It is to definitively know what the baseline work is worth. The lowest price means nothing until you know what it leaves out.